INDUSTRIAL CONNECTION APPLICATION FORM


Welcome!

To begin your Industrial Connection Application process, please provide your mobile number:
e.g. 923001234567

Application Process Flow & Timelines

(Where Distribution Network Exists)

Application Submission & Verification
04 Days
HSE Clearance (Initial LOP)
05 Days
Issuance of Internal House Line Quotation
06 Days
Internal Job Execution (Distribution Department)
30 Days
Pre-Commissioning
07 Days
SITE Survey
10 Days
Planning Clearance
06 Days
Payment receiving & Processing for Job
10 Days
HSE Clearance (Structural)
07 Days
Commissioning
05 Days

Note: Above time-lines are subject to completion of formalities, completion of civil work, payments, road cutting, procurement of equipment by customer.
Total Time Elapsed: 90 Days


Where Mains Network Extension Required

Application Submission & Verification
04 Days
HSE Clearance (Initial LOP)
05 Days
Mains Payment Receiving & Processing for Job
12 Days
Issuance of Internal House Line Quotation
06 Days
Internal Job Execution (Distribution Department)
30 Days
Pre-Commissioning
07 Days
SITE Survey
10 Days
Mains Planning / Approval / Quotation
24 Days
Mains Job Execution (P&D & Distribution Department)
60 Days
Payment receiving & Processing for Job
10 Days
HSE Clearance (Structural)
07 Days
Commissioning
05 Days

Note: Above time-lines are subject to completion of formalities, completion of civil work, payments, road cutting, procurement of equipment by customer.
Total Time Elapsed: 180 Days